INDUSTRIAL + COMMERCIAL · UTAH & IDAHO(385) 390-0743
RC▰COATINGSROOFS + FLOORS
All case studiesMeat-processing facility
Meat-processing facility / Project case study

A failed dairy-brick corridor restored within the shutdown

A deteriorated traffic corridor was rebuilt while coordinating unexpected plumbing work, with the floor returned to service within a Friday-to-Sunday shutdown.

Friday–SundayShutdown window
150 LFApproximate plumbing trench length
1 inchHand-troweled urethane cement

The challenge

The flooring repair grew when deteriorated plumbing was discovered beneath the failure zone. Plumbing replacement required an approximately four-foot-wide, 150-foot-long trench. Work began early Friday and needed to finish by Sunday afternoon to meet production scheduling and cure-time requirements.

The work

As plumbing ran beyond schedule, RC Coatings took on portions of road-base preparation and compaction to maintain the concrete placement sequence. The documented assembly included four inches of rapid-set concrete, mechanical surface preparation and keyway cuts, one inch of hand-troweled Poly-Crete WR, a sand broadcast and two Poly-Crete TF topcoats.

The result

The restored corridor returned to service within the shutdown window. The repair extended toward the forklift doorway to remove transition lips and create a flush floor for heavy traffic and washdown exposure. Follow-on testing of a separate overlay approach was exploratory and is not presented as part of this completed repair.

Start with the building

Tell us what needs
to work better.

A recurring leak. A worn processing floor. A capital project on the horizon. Let’s look at the conditions and the options.

Request a site assessment